Quetta Airport Main Runway to be Reconstructed
-
- Site Admin
- Posts: 52155
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Quetta Airport Main Runway to be Reconstructed
From April 20 to September 29:
Reconstruction (Phase I) will commence on main Runway 13L/31R on 570M from beginning of Runway 31R. With effect from April 20, 2020, the runway end will be shifted accordingly.
Abbas
-
- Site Admin
- Posts: 52155
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Quetta Airport Main Runway to be Reconstructed
May 5, 2020, to October 14, 2020, owing to prevailing circumstances in the country due to COVID-19, reconstruction work shall now commence on main Runway 13L/31R on 670M from begining of Runway 31R with effect from May 5, 2020. The runway end shall accordingly be shifted temporarily.
Abbas
Abbas
-
- Site Admin
- Posts: 52155
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Quetta Airport Main Runway to be Reconstructed
June 3, 2020, to October 14, 2020, Instrument Landing System (ILS) approach Runway 13L will not be available due to work to upgrade main Runway 13L/31R.
Abbas
Abbas
-
- Site Admin
- Posts: 52155
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Quetta Airport Main Runway to be Reconstructed
From September 16 to October 14.
Reconstruction work phase (1B) shall commence on main Runway 13L/31R on 963.8 meters from beginning of Runway 31R. The runway end will be shifted accordingly.
Abbas
Reconstruction work phase (1B) shall commence on main Runway 13L/31R on 963.8 meters from beginning of Runway 31R. The runway end will be shifted accordingly.
Abbas
-
- Site Admin
- Posts: 52155
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Quetta Airport Main Runway to be Reconstructed
From September 19 to September 22.
Quetta Airport Runway 31R Precision Approach Path Indicator (PAPI), threshold and runway end lights will not be available for operations due to shifting of these facilities.
B)2009181100 C)2009190400
E)RWY WILL NOT BE AVBL FOR OPS DUE TO RECONSTRUCTION WORK
(PHASE 1B) ON MAIN RWY 13L/31R.)
Earlier, from September 18 to September 19
Quetta Airport Runway 13L/31R was not available for flight operations due to runway reconstruction work Phase 1B.
Abbas
Quetta Airport Runway 31R Precision Approach Path Indicator (PAPI), threshold and runway end lights will not be available for operations due to shifting of these facilities.
B)2009181100 C)2009190400
E)RWY WILL NOT BE AVBL FOR OPS DUE TO RECONSTRUCTION WORK
(PHASE 1B) ON MAIN RWY 13L/31R.)
Earlier, from September 18 to September 19
Quetta Airport Runway 13L/31R was not available for flight operations due to runway reconstruction work Phase 1B.
Abbas
-
- Site Admin
- Posts: 52155
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Quetta Airport Main Runway to be Reconstructed
From September 23, 2020, to March 31, 2021.
During re-construction work (Phase-1) of main runway, revised runway slope will be as follows:
Runway 13L (+) 0.467 percent for 1st half then (+) 0.736 Percent for 3rd quarter then (+) 0.83 percent for last Quarter.
Runway 31R (-) 0.83 percent for 1st quarter then (-) 0.736 Percent for 2nd quarter then (-) 0.467 percent for remaining half of the runway.)
Abbas
During re-construction work (Phase-1) of main runway, revised runway slope will be as follows:
Runway 13L (+) 0.467 percent for 1st half then (+) 0.736 Percent for 3rd quarter then (+) 0.83 percent for last Quarter.
Runway 31R (-) 0.83 percent for 1st quarter then (-) 0.736 Percent for 2nd quarter then (-) 0.467 percent for remaining half of the runway.)
Abbas
-
- Site Admin
- Posts: 52155
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Quetta Airport Main Runway to be Reconstructed
From September 28 to October 31
Reconstruction work phase (1B) shall commence on main Runway 13L/31R on 963.8 meters from beginning of Runway 31R.
The runway end shall accordingly be shifted temporarily.
Abbas
Reconstruction work phase (1B) shall commence on main Runway 13L/31R on 963.8 meters from beginning of Runway 31R.
The runway end shall accordingly be shifted temporarily.
Abbas
-
- Site Admin
- Posts: 52155
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Quetta Airport Main Runway to be Reconstructed
From October 6 to November 5.
Digging work in progress from edge of beginning of Runway 31 towards northern B2 link taxi up to a distance of 300 feet. All aircraft to exercise caution for landing/takeoff and taxiing on main runway.
Abbas
Digging work in progress from edge of beginning of Runway 31 towards northern B2 link taxi up to a distance of 300 feet. All aircraft to exercise caution for landing/takeoff and taxiing on main runway.
Abbas
-
- Site Admin
- Posts: 52155
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Quetta Airport Main Runway to be Reconstructed
From October 9 to November 9.
Heavy machinery deployed undershoot Runway 31R due to work in progress. All pilots advised to exercise caution while taxiing.
Abbas
Heavy machinery deployed undershoot Runway 31R due to work in progress. All pilots advised to exercise caution while taxiing.
Abbas
-
- Site Admin
- Posts: 52155
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Quetta Airport Main Runway to be Reconstructed
From October 13, 2020, to January 14, 2021.
Instrument Landing System (ILS) approach Runway 13L will not be available due to upgrading of main Runway 13L/31R.
Abbas
Instrument Landing System (ILS) approach Runway 13L will not be available due to upgrading of main Runway 13L/31R.
Abbas
-
- Site Admin
- Posts: 52155
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Quetta Airport Main Runway to be Reconstructed
From October 28, 2020, to January 31, 2021
Reconstruction work phase (1B) shall commence on main Runway 13L/31R on 963.8 meters from beginning of Runway 31R.
The runway end shall accordingly be shifted temporarily.
Revised distance available would be as follows:
Abbas
Reconstruction work phase (1B) shall commence on main Runway 13L/31R on 963.8 meters from beginning of Runway 31R.
The runway end shall accordingly be shifted temporarily.
Revised distance available would be as follows:
Abbas
-
- Site Admin
- Posts: 52155
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Quetta Airport Main Runway to be Reconstructed
From November 5, 2020, to February 5, 2021.
Digging work in progress from edge of beginning of Runway 31 towards northern B2 link taxi up to a distance of 300 feet. All aircraft to exercise caution for landing/takeoff and taxiing on main runway.
Abbas
Digging work in progress from edge of beginning of Runway 31 towards northern B2 link taxi up to a distance of 300 feet. All aircraft to exercise caution for landing/takeoff and taxiing on main runway.
Abbas
-
- Site Admin
- Posts: 52155
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Quetta Airport Main Runway to be Reconstructed
Construction work seen at Quetta International Airport - Photo by Ameer Jan
Thank you Ameer for sharing!
Abbas
-
- Site Admin
- Posts: 52155
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Quetta Airport Main Runway to be Reconstructed
From November 9, 2020, to March 31, 2021.
Heavy machinery deployed undershoot Runway 31R due to work in progress. All pilots advised to exercise caution while landing.
Abbas
Heavy machinery deployed undershoot Runway 31R due to work in progress. All pilots advised to exercise caution while landing.
Abbas
-
- Site Admin
- Posts: 52155
- Joined: Thu Aug 05, 2004 6:52 pm
- Location: Pakistan
Re: Quetta Airport Main Runway to be Reconstructed
Quetta International Airport main Runway 13L/31R reconstruction photos taken by Ameer Jan.
Thank you Ameer for sharing!
Abbas
Thank you Ameer for sharing!
Abbas