Lahore Airport Runways, Taxiways and Apron Maintenance Work

Discuss issues and news related to PIA, Pakistani airlines and Pakistan's civil & military aviation.
User avatar
Abbas Ali
Site Admin
Posts: 52285
Joined: Thu Aug 05, 2004 6:52 pm
Location: Pakistan

Re: Lahore Airport Runways, Taxiways and Apron Maintenance Work

Post by Abbas Ali »

Pakistan Civil Aviation Authority (CAA) tender notice in June 11 newspaper for replacement of existing damaged perimeter fence at 36 end towards Nadirabad at Allama Iqbal International Air Port (AIIAP) - Lahore.

Image

Abbas
Dil Dil Pakistan... Jaan Jaan Pakistan

See you at:
Image
User avatar
Abbas Ali
Site Admin
Posts: 52285
Joined: Thu Aug 05, 2004 6:52 pm
Location: Pakistan

Re: Lahore Airport Runways, Taxiways and Apron Maintenance Work

Post by Abbas Ali »

Lahore Airport Chief Operating Officer/Airport Manager has requested for slot timings for repair and maintenance of airport's main Runway 36R/18L facing very frequent patch eruption.

Main Runway 36R/18L has been facing very frequent patch eruption which is being treated by Civil (M&D) with immediate and remedial action. However Pavement Quality Concrete (PQC) surface has not been able to to sustain the bearing load of the aircraft in the critical area of touch down near Taxiway Tango which had been highlighted many times before the higher authority.

In this connection, available slot timings are required to repair the said area and the part of runway for which slot timings had been provided by ANS Section during which no flight will be affected as Runway 36L will be available for aircraft lower than Airbus A300 and Boeing 777.

Details of slot timings is as under:

Day Monday
Timings (UTC) 0615-1200

Day Tuesday
Timings (UTC) 0615-0915

Day Wednesday
Timings (UTC) 0745-1300

Day Thursday
Timings (UTC) 0630-1055

Day Friday
Timings (UTC) Less than 3 hours

During slot timings, secondary runway will be available for arriving and departing aircraft. Main Runway 36R will not be available during slot timings. However, in case of emergency, the main runway will be available 15 minutes prior to the notice.

It is request to accord for issuance of NOTAM for above mentioned timings for repair/maintenance of Runway 36R for a period of seven working days with effect August 1 to 9, 2019 (Saturday and Sunday excluded) as early as possible to start the work.



Abbas
Dil Dil Pakistan... Jaan Jaan Pakistan

See you at:
Image
User avatar
Abbas Ali
Site Admin
Posts: 52285
Joined: Thu Aug 05, 2004 6:52 pm
Location: Pakistan

Re: Lahore Airport Runways, Taxiways and Apron Maintenance Work

Post by Abbas Ali »

NOTAM issued.

Lahore Airport main Runway 36R/18L will remain closed for repair and maintenance for seven working days from August 1 to August 9 (Saturday & Sunday excluded). Secondary Runway 36L/18R will be available during closures. However, in case of emergency, main runway will be available at 15 minutes prior notice.

Runway 36R/18L repair/maintenance work days and timings in UTC.

Monday 0615-1200
Tuesday 0615-0915
Wednesday 0745-1300
Thursday 0630-1055
Friday (Less than three hours)

Image

Abbas
Dil Dil Pakistan... Jaan Jaan Pakistan

See you at:
Image
User avatar
Abbas Ali
Site Admin
Posts: 52285
Joined: Thu Aug 05, 2004 6:52 pm
Location: Pakistan

Re: Lahore Airport Runways, Taxiways and Apron Maintenance Work

Post by Abbas Ali »

Pakistan Civil Aviation Authority (CAA) tender notice in October 18 newspaper for replacement of existing damaged perimeter fence at 36 end towards Nadirabad at Allama Iqbal International Air Port (AIIAP) - Lahore.

Image

Abbas
Dil Dil Pakistan... Jaan Jaan Pakistan

See you at:
Image
User avatar
Abbas Ali
Site Admin
Posts: 52285
Joined: Thu Aug 05, 2004 6:52 pm
Location: Pakistan

Re: Lahore Airport Runways, Taxiways and Apron Maintenance Work

Post by Abbas Ali »

Pakistan Civil Aviation Authority (CAA) tender notice in December 5 newspaper for remarking/repainting of apron vehicular tracks and business roads at Allama Iqbal International Air Port (AIIAP) - Lahore.

Image

Abbas
Dil Dil Pakistan... Jaan Jaan Pakistan

See you at:
Image
User avatar
Abbas Ali
Site Admin
Posts: 52285
Joined: Thu Aug 05, 2004 6:52 pm
Location: Pakistan

Re: Lahore Airport Runways, Taxiways and Apron Maintenance Work

Post by Abbas Ali »

According to NOTAM issued by Pakistan CAA.

On December 23, Lahore Airport main Runway 36R/18L will be closed for flight operations for maintenance/repairs work between 10:00 AM to 6:00 PM.

During main runway closure, secondary Runway 36L/18R will be available for flight operations. Airlines are advised to operate aircraft according to strength of secondary Runway 36L/18R having Pavement Classification Number (PCN) value 69/F/C/Y/T.

Image

Lahore Airport Runways

Main Runway 18L/36R measuring 11000 feet x 150 feet - concrete surface.

Secondary Runway 18R/36L measuring 9000 feet x 150 feet - asphalt surface.

Image

According to NOTAM issued by Pakistan CAA.

From December 17 to January 16 aircraft operations compatible with PCN 69/F/C/Y/T shall be carried out on secondary Runway 36L/18R due to main Runway 36R/18L repairs and maintenance work.

Tuesday between 3:20 PM and 5:40 PM
Wednesday between 10:35 PM and 3:10 PM
Thursday between 2:40 PM and 5:00 PM
Friday between 10:10 AM and 1:00 PM
Saturday between 12:50 PM and 4:40 PM

However, during limited weather conditions main Runway 36R/18L may be used having PCN 85/R/B/X/U.

Image

Abbas
Dil Dil Pakistan... Jaan Jaan Pakistan

See you at:
Image
User avatar
Omairi7
Registered Member
Posts: 351
Joined: Sat Apr 18, 2015 11:33 am
Location: Lahore

Re: Lahore Airport Runways, Taxiways and Apron Maintenance Work

Post by Omairi7 »

Abbas Ali wrote: Mon Dec 16, 2019 11:25 am According to NOTAM issued by Pakistan CAA.

On December 23, Lahore Airport main Runway 36R/18L will be closed for flight operations for maintenance/repairs work between 10:00 AM to 6:00 PM.

During main runway closure, secondary Runway 36L/18R will be available for flight operations. Airlines are advised to operate aircraft according to strength of secondary Runway 36L/18R having Pavement Classification Number (PCN) value 69/F/C/Y/T.

Image

Lahore Airport Runways

Main Runway 18L/36R measuring 11000 feet x 150 feet - concrete surface.

Secondary Runway 18R/36L measuring 9000 feet x 150 feet - asphalt surface.

Image

According to NOTAM issued by Pakistan CAA.

From December 17 to January 16 aircraft operations compatible with PCN 69/F/C/Y/T shall be carried out on secondary Runway 36L/18R due to main Runway 36R/18L repairs and maintenance work.

Tuesday between 3:20 PM and 5:40 PM
Wednesday between 10:35 PM and 3:10 PM
Thursday between 2:40 PM and 5:00 PM
Friday between 10:10 AM and 1:00 PM
Saturday between 12:50 PM and 4:40 PM

However, during limited weather conditions main Runway 36R/18L may be used having PCN 85/R/B/X/U.

Image

Abbas


Abbas bhai , do you really think this is the worst time especially during FOG season when things are always out of control and yet they are again playing with the runway. The whole summer season needs to be utilized for resurfacing or upgrading so winters can easy manageable.
EK, EY, SV, PK, AIR BLUE, EASY JET, AA, TG, MH, FLY BE, VUELING, SAS, SWISS, LH, BA, AIR BERLIN, RYAN AIR, GERMAN WINGS, JET BLUE, U.A, QATAR , AZAL ...
User avatar
Abbas Ali
Site Admin
Posts: 52285
Joined: Thu Aug 05, 2004 6:52 pm
Location: Pakistan

Re: Lahore Airport Runways, Taxiways and Apron Maintenance Work

Post by Abbas Ali »

According to NOTAM issued by Pakistan CAA:

From December 20, 2019 to January 16, 2020, Lahore Airport main Runway 36R/18L will remain closed due to repairs and maintenance works as per following schedule. Irrespective of above mentioned schedule, aircraft operations compatible with PCN 69/F/C/Y/T shall be carried out on secondary Runway 36L/18R.

However during landing, weather conditions or due to operational reason main Runway 36R/18L may be used/offered. Aircraft operations compatible with main Runway 36R/18L PCN 85/R/B/X/U to observe its non-availability during mentioned specific hours.

Tuesday from 3:20 PM to 5:40 PM
Wednesday from 10:35 AM to 3:10 PM
Thursday from 2:40 PM to 5:00 PM
Friday from 10:10 AM to 1:00 PM
Saturday from 12:50 PM to 4:40 PM

Image

Abbas
Dil Dil Pakistan... Jaan Jaan Pakistan

See you at:
Image
User avatar
Abbas Ali
Site Admin
Posts: 52285
Joined: Thu Aug 05, 2004 6:52 pm
Location: Pakistan

Re: Lahore Airport Runways, Taxiways and Apron Maintenance Work

Post by Abbas Ali »

According to NOTAM issued by Pakistan CAA:

From January 15 to February 14 Lahore Airport main Runway 36R/18L shall remain closed due to repairs and maintenance works. As per schedule given below. Irrespective of the given schedule aircraft operations compatible with PCN 69/F/C/Y/T shall be carried out on secondary Runway 36L/18R. However during limited weather conditions or due to operational reason main Runway 36R/18L may be used/offered. Aircraft operations compatible with main runway PCN 85/R/B/X/U to observe its non-availability during mentioned specific hours.

Tuesday from 3:20 PM to 5:40 PM
Wednesday from 10:35 AM to 3:10 PM
Thursday from 2:40 PM to 5:00 PM
Friday from 10:10 AM to 1:00 PM
SAT from 12:50 PM to 4:40 PM

Image

Abbas
Dil Dil Pakistan... Jaan Jaan Pakistan

See you at:
Image
User avatar
Abbas Ali
Site Admin
Posts: 52285
Joined: Thu Aug 05, 2004 6:52 pm
Location: Pakistan

Re: Lahore Airport Runways, Taxiways and Apron Maintenance Work

Post by Abbas Ali »

According to NOTAM issued by Pakistan CAA:

Image

From February 13 to March 15 Lahore Airport main Runway 36R/18L shall remain closed due to repairs and maintenance works. As per schedule given below. Irrespective of the given schedule, aircraft operations compatible with PCN 69/F/C/Y/T shall be carried out on secondary Runway 36L/18R.

However, during limited weather conditions or due to operational reasons, main Runway 36R/18L may be used/offered. Aircraft operations compatible with main runway PCN 85/R/B/X/U to observe its non-availability during mentioned specific hours.

Tuesday from 3:20 PM to 5:40 PM
Wednesday from 10:35 AM to 3:10 PM
Thursday from 2:40 PM to 5:00 PM
Friday from 10:10 AM to 1:00 PM
Saturday from 12:50 PM to 4:40 PM

Abbas
Dil Dil Pakistan... Jaan Jaan Pakistan

See you at:
Image
User avatar
Abbas Ali
Site Admin
Posts: 52285
Joined: Thu Aug 05, 2004 6:52 pm
Location: Pakistan

Re: Lahore Airport Runways, Taxiways and Apron Maintenance Work

Post by Abbas Ali »

From March 15 to April 20 Lahore Airport main Runway 36R/18L will be closed for two hours daily for civil works as per schedule given below:

Image

Abbas
Dil Dil Pakistan... Jaan Jaan Pakistan

See you at:
Image
User avatar
Abbas Ali
Site Admin
Posts: 52285
Joined: Thu Aug 05, 2004 6:52 pm
Location: Pakistan

Re: Lahore Airport Runways, Taxiways and Apron Maintenance Work

Post by Abbas Ali »

From March 30 to September 30, Taxiway H will not be available for indefinite period due to rehabilitation work. However first 300 feet of Taxiway H link till Taxiway K link junction is available for taxiing in/out for Pakistan Air Force (PAF) tarmac. All aircraft to follow Taxiway K while taxiing in and out of PAF tarmac.

Image

Abbas
Dil Dil Pakistan... Jaan Jaan Pakistan

See you at:
Image
User avatar
Abbas Ali
Site Admin
Posts: 52285
Joined: Thu Aug 05, 2004 6:52 pm
Location: Pakistan

Re: Lahore Airport Runways, Taxiways and Apron Maintenance Work

Post by Abbas Ali »

From April 24 to June 4, Lahore Airport primary Runway 36R/18L shall remain closed for two hours daily for civil maintenance works. The airport's secondary Runway 36L/18R (having PCN VALUE 69/F/C/Y/T) shall remain available during primary runway closure timings.

Image

Abbas
Dil Dil Pakistan... Jaan Jaan Pakistan

See you at:
Image
User avatar
Abbas Ali
Site Admin
Posts: 52285
Joined: Thu Aug 05, 2004 6:52 pm
Location: Pakistan

Re: Lahore Airport Runways, Taxiways and Apron Maintenance Work

Post by Abbas Ali »

April 30 to July 31

Bay Number 29 and 30 at Lahore Airport will not be available for parking aircraft due to rehabilitation work.

Image

Abbas
Dil Dil Pakistan... Jaan Jaan Pakistan

See you at:
Image
User avatar
Abbas Ali
Site Admin
Posts: 52285
Joined: Thu Aug 05, 2004 6:52 pm
Location: Pakistan

Re: Lahore Airport Runways, Taxiways and Apron Maintenance Work

Post by Abbas Ali »

From June 3, 2020, to August 3, 2020, Lahore Airport primary Runway 36R/18L shall remain closed for two hours daily for civil maintenance works. The airport's secondary Runway 36L/18R (having PCN VALUE 69/F/C/Y/T) shall remain available during primary runway closure timings.

Image

Abbas
Dil Dil Pakistan... Jaan Jaan Pakistan

See you at:
Image